- DL/T5161.3-2002电气装置安装工程质量检验及评定规程第3部分:电力变压器、油浸电抗器、互感器施工质量检验(英文版)
- 中国电力企业联合会
- 302字
- 2021-04-01 14:07:01
1 Installation of Power Transformer(Oil Immersed Reactor)
1.0.1 Installation and inspection of dry-type transformer with 35kV and below(see Table 1.0.1).
Table 1.0.1 Installation of dry-type transformer
1.0.2 Installation and inspection for oil immersed transformer and reactor of rated capacity of 1600kV·A(kvar)and below is shown below(see Table 1.0.2).
Table 1.0.2 Installation of oil immersed transformer of rated capacity up to and including 1600kV·A
Table 1.0.2(continued)
1.0.3 This sub-clause is applicable to the installation of oil immersed transformer and oil immersed reactor with rated capacity above 1600kV·A(kvar).
1.0.3-1 Checkout on proper installation of oil immersed transformer(oil immersed reactor)with medium capacity above 1600kV·A(kvar)is listed in Table 1.0.3-1.
Table 1.0.3-1 Proper installation of oil immersed transformer above medium capacity
1.0.3-2 Checkout on oil immersed transformer(oil immersed reactor)above medium capacity is shown in Table 1.0.3-2.
Table 1.0.3-2 Checkout on oil immersed transformer above,edium capacity
Table 1.0.3-2(continued)
1.0.3-3 Checkout on accessories installation of oil immersed transformer(oil immersed reactor)above medium capacity is shown in Table 1.0.3-3.
Table 1.0.3-3 Accessories installation of oil immersed transformer above medium capacity
Table 1.0.3-3(continued)
Table 1.0.3-3(continued)
1.0.3-4 Oil injection and seal test of oil immersed transformer(oil immersed reactor)of medium capacity and above is shown in Table 1.0.3-4.
Table 1.0.3-4 Oil injection and sealing test of oil immersed transformer above medium capacity
1.0.3-5 Overall checkout on oil immersed transformer(oil immersed reactor)above medium capacity(see Table 1.0.3-5).
Table 1.0.3-5 Overall checkout on oil immersed transformer above medium capacity