4.6 Project Acceptance
4.6.1 For the quality acceptance for waste heat boiler project installation,the main control items of test batches shall include the following contents:
1 Boiler foundation positioning;
2 Boiler steel frame assembly and installation;
3 Installation for boiler proper doors and holes,part of sealing elements;
4 Installation of ash hopper and dust collection device;
5 Installation of drum and header;
6 Installation of heating surface(economizer,evaporator,superheater);
7 Installation of de-ashing device;
8 Pressure test for the entire boiler.
4.6.2 The issued certificates for boiler installation shall include the following contents:
1 Records and certificate for concealed project construction;
2 Certificate for ball passing test for heating surface tubes;
3 Qualified certificate for boiler pressure test;
4 Completion certificate for de-ashing rapping system and tests;
5 Certificate for steam tightness test.
4.6.3 While carrying out acceptance for waste heat boiler installation,the following documentation are required to be submitted:
1 Record for equipment open-package inspection;
2 Reviewing record for alloy steel pipelines and pipe fittings;
3 Reviewing record for boiler foundation;
4 Record for boiler steel frame assembly and installation;
5 Record for economizer assembly and installation;
6 Record for evaporator assembly and installation;
7 Record for superheater assembly and installation;
8 Record for drum installation;
9 Checking record for installation of drum internal devices;
10 Installation record for main hot expansion displacement components;
11 Checking record for heat expansion clearance of heating surface;
12 Checking record for safety valve checking;
13 Report for nondestructive inspection for boiler proper welding;
14 Boiler installation supervision and inspection certificate;
15 Acceptance record for subdivisional work;
16 Effective technical documentation list and original documentation for design alternation and substitute materials;
17 The certificates required by Article 4.6.2 of this code;
18 Other required documentation and records.